Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 14°C, mostly cloudy
Workers onsite: At least 6
Work done today:
- More demolition of the central courtyard area and extending out to the edge of the visitor parking lot
- The temporary bridge/path for the 244 building is now open