Phase 2 membrane project, Day 17–August 8, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 25°C, sunny
Workers onsite: At least two

Work done today:

  • Additional work on the patios around the 240 and 244 buildings

Leave a Comment