Weather: 29°C, mostly cloudy
Workers onsite: At least 4-6
Work done today:
- Sand is being laid in the Phase 1 extension area. This is the final step before pavers are put back.
- Aeration (drainage) mat and root barrier are being installed in the emergency repair area.
- Additional work was done to address deficiencies and unfinished parts of the emergency area.
- New wooden beams, part of the architectural detail, have been brought in for both areas.
In addition, the bi-weekly onsite meeting took place between all parties:
- Strata Engineering
- Prostar
- Copperstone Council (represented by the President and Vice President)
- Quay Pacific was not able to attend
Issues with site safety and storage were discussed and addressed. As part of this, all material on the easement facing Brunette Avenue has been removed.