Weather: 24°C, sunny
Workers onsite: At least 4-6
Work done today:
- Blue Drop installed irrigation piping in the emergency repair area.
- Additional work on the emergency repair area to install aeration mat and placement of wooden beams.
- Sidewalk from staircase and Allan blocks both extended in the Phase 1 extension.
- Wooden beams placed in Phase 1 extension.