Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.
An UNOFFICIAL site for Copperstone, New Westminster
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.
It’s the end of the second week of the project and as far as I can tell, there has been no update from Strata Engineering, Prostar, Quay Pacific or Copperstone Council on why nothing is happening.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.