Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 7C, rain
UPDATE, February 22: It appears someone came onsite to put the cover plate on the south lamp post between the 244 and 248 buildings. I'm not sure when this happened, but it was within the past few days. See photo below, taken Sunday, February 22.

No work onsite today, pending decisions on remaining work.