Phase 1 Membrane Project, Day 15 (September 16, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 29C, sunny

Work done today:

  • Further plumbing work on the three new drains done by Highmark Plumbing

Phase 1 Membrane Project, Day 14 (September 15, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 21C, mostly sunny

Work done today:

  • A plumbing company and other workers spent time working on the new drains that were drilled, along with the piping underneath in the underground parking lot.

Phase 1 Membrane Project, Day 13 (September 13, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23C, clouds in morning, sun in afternoon

No work onsite today.

Phase 1 Membrane Project, Day 12 (September 12, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23C, Clouds in morning, clearing in afternoon

Some people observed in the work area in the morning and afternoon, but otherwise, no work onsite today.

Phase 1 Membrane Project, Day 11 (September 11, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23C, sun and clouds

Work done today:

  • All remaining patios facing the retaining wall have had their pavers removed.
  • Core drilling was done to place holes for three new drains in the membrane area (see below for photos). These extend through to the underground parking below and will be connected to the pipe system.
  • Additional preparation was done for the upcoming concrete work.

Unfortunately, the equipment used for the drilling was plugged into an outlet on our patio and tripped the breaker, killing power in our unit.

Also, some trash was left behind that is not part of the construction project.

Phase 1 Membrane Project, Day 10 (September 10, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23C, sun and cloud mix

Work done today:

  • The ground surface behind the 244 building was hosed down.
  • All trees, bushes and other vegetation from between the 244 and 248 buildings were removed.
  • Wooden beams alongside the 248 building were removed.
  • Additional Allan blocks have been temporarily stored in the central courtyard (visitor parking).