Phase 1 Membrane Project, Day 87 (December 12, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 8C, drizzle and cloud, some showers

Work done today:

  • More pavers returned to the patios. At this point, all five patios have the majority of the pavers restored. The boarding and stone cladding work remains to be done.
  • Workers onsite: At least four.

Phase 1 Membrane Project, Day 86 (December 11, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, cloudy with isolated showers

Work done today:

  • Further work on extending membrane around the lamp posts and base of the staircase between the 244 and 248 buildings.
  • Workers onsite: At least four observed.

Phase 1 Membrane Project, Day 85 (December 10, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, heavy rain

There were people onsite today, but I believe it was mostly site inspection and moving some equipment out of the rain or to other areas.