Phase 1 Membrane Project, Day 49 (October 28, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, showers and clouds

Work done today:

  • No work observed around the concrete slab behind the 244 building or between the 244 and 248 buildings.
  • Some preliminary work for the new replacement drains was apparently done in the 244 parkade early in the evening (plumbers were observed in the area).

The site as of Tuesday, October 28, 2025:

Phase 1 Membrane Project, Day 48 (October 27, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, clouds and showers

Work done today:

  • Additional removal of stone cladding from several pillars adjacent to the 244 building patios.
  • Wood forms moved in place near the retaining wall behind the 244 building (the area is not clean/ready for a concrete pour, so this may just be temporary).
  • Workers onsite: 3 observed, possibly more.

Phase 1 Membrane Project, Day 47 (October 25, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, rain, gusting wind at times, clouds

Work done today:

  • Shot blasting of the exposed portion beneath the Allan block wall behind the 244 building, in preparation for the concrete curb that will go in the same area.
  • Workers onsite: At least four observed.

Shot blasting material used was Enviro-Grit Abrasives Enviro-Grit. The product page is here: https://www.enviro-corp.ca/enviro-grit. It’s basically extra fine glass dust.

The photo below was taken from our patio.

NOTE: The work crew was still here at 8 p.m., which appears to be a violation of New Westminster City Bylaw 8013, part of City Bylaw 6063 (Construction Noise):

Bylaw 6063 can be viewed as a PDF here: https://www.newwestcity.ca/database/files/library/Consolidated_Bylaw_6063__1992_Construction_Noise(1).pdf

Phase 1 Membrane Project, Day 46 (October 24, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 13C, heavy rain and wind

Work done today:

  • Removal of planking along the bottom of the 244 building on the west and north sides.
  • Removal of the lower portion of stone cladding from the pillars in the areas listed above.
    • This work is being done to allow the new membrane to extend eight inches (about 20 cm).
  • Workers onsite today: At least four observed.
  • Strata Engineering also had at least four people onsite doing inspections.

Phase 1 Membrane Project, Day 45 (October 23, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 15C, mix of cloud and showers

Work done today:

  • Continued removal of membrane residue from concrete slab behind the 244 building and between the 244 and 248 buildings.
  • Power-washing of concrete slab between the 244 and 248 buildings.
  • Workers onsite: At least 3.

Phase 1 Membrane Project, Day 44 (October 22, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 12C, cloudy, some showers

Work done today:

  • Continued removal of membrane residue between the 244 and 248 buildings and along the back (west) side of the 244 building.
  • Work expanded to patios, with all but one patio in various states of having all membrane residue removed.
  • Workers observed: At least three.

Additional work to be done before new membrane can be installed (incomplete list):

  • Removal of lowest planking on the back of the 244 building, to allow expanded membrane coverage.
  • Removal of lower portion of stone cladding through same area as above (you can see an example of this removal in the first photo below).
  • Blasting of both of the above exposed surface areas, to allow clean installation of new membrane.
  • Additional membrane residue removal along edges in various areas.