Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 7C, mostly sunny
Another unexpected day of work during the holiday break.
Work done today:
More finishing work on the metal flashing and restoring the planking around patios. I believe the intention is to have the patios fully complete in the next 1-2 business days.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 7C, overcast
An unexpected work day over the holiday break.
Work done today:
Additional work on finishing the metal flashing around the pillars and base of the 244 building.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
NOTE: Work on the membrane project will be on hold over the Christmas holiday. It will resume on January 3, 2026, with completion of the project expected before the end of January.
More details on the remaining work will be posted soon.
Weather: 6C, cloudy
Today was supposed to be the first day of the holiday break for Prostar, but workers were back onsite.
Work done today:
Additional clean-up of area.
Metal flashing applied along the base of the stone-clad pillars on the 244 building.
Workers onsite today: At least five.
Metal flashing on the base of the pillars, membrane material applied along perimter adjacent to parking lot.The site as of December 23, 2025.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 7C, clouds and showers
Work done today:
More Allan blocks placed between the 244 and 248 buildings to re-establish the planters.
The reglet cut along the concrete curb was widened to bring it up to spec.
Gravel and other material were cleaned out of the four central parking spaces, meaning all parking stalls in visitor parking are again available.
Workers onsite: At least five.
Four parking stalls re-opened to visitor parking again.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 6C, rain, some clouds
Work done today:
Setting Allan blocks along the pavers for the sidewalk leading to the staircase. The blocks will form the planters that were previously located here.
Added wooden beams around vertical pipes adjacent to the 248 building.
Membrane material applied to concrete pads at the base of the staircase.
Workers onsite: At least two.
Pavers being placed for the sidewalk, Allan blocks being put back as part of a large planter/raised area.Close-up showing application of membrane material to sleepers/concrete pads at the base of the stairs. also visible is the aeration mat. Soil will be placed on top of this.