Phase 1 Membrane Project, Day 13 (September 13, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23C, clouds in morning, sun in afternoon

No work onsite today.

Phase 1 Membrane Project, Day 12 (September 12, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23C, Clouds in morning, clearing in afternoon

Some people observed in the work area in the morning and afternoon, but otherwise, no work onsite today.

Phase 1 Membrane Project, Day 11 (September 11, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23C, sun and clouds

Work done today:

  • All remaining patios facing the retaining wall have had their pavers removed.
  • Core drilling was done to place holes for three new drains in the membrane area (see below for photos). These extend through to the underground parking below and will be connected to the pipe system.
  • Additional preparation was done for the upcoming concrete work.

Unfortunately, the equipment used for the drilling was plugged into an outlet on our patio and tripped the breaker, killing power in our unit.

Also, some trash was left behind that is not part of the construction project.

Phase 1 Membrane Project, Day 10 (September 10, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23C, sun and cloud mix

Work done today:

  • The ground surface behind the 244 building was hosed down.
  • All trees, bushes and other vegetation from between the 244 and 248 buildings were removed.
  • Wooden beams alongside the 248 building were removed.
  • Additional Allan blocks have been temporarily stored in the central courtyard (visitor parking).

Phase 1 Membrane Project Day 9 (September 9, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: Sun and cloud, 23C

Work done:

  • The area adjacent to the 248 building had its soil, flowers, vegetation and trees removed.
  • The Allan blocks1 between the 244 and 248 buildings have been removed. All blocks filled with cement have been disposed of, as they can’t be re-used (ones filled with dirt can be kept and re-used).
  • Pavers forming the sidewalk leading to the staircase have been removed and stored in the central courtyard (visitor parking).

The number of workers onsite appeared to be 4-6.

  1. Allan blocks look like this: ↩︎

Phase 1 Membrane Project, Day 8 (September 8, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23C, sun and cloud mix

No work done onsite today. The first bi-weekly status meeting took place involving:

  • Prostar
  • Strata Engineering
  • Sub contractor reps
  • Copperstone Council (President and Vice President attending)

Based on discussions, clean-up of the work area should be complete in the next few days, after which the forms for concrete will be placed, and then concrete poured. If the weather turns wet, tarps will likely be put in place to allow the concrete to remain dry while it cures.

Prostar is suggesting that the old structure of wooden beams/gravel fill along the perimeter of the back of the 244 building be replaced with soil and grass (extending the lawn right to the edge of the building and patios). The wood and grass was an architectural feature, but has essentially no visibility, as it faces the retaining wall. Extending the lawn to the building would be cheaper and provide a more uniform look. This will be brought to council for a final decision.