Phase 1 Membrane Project Day 9 (September 9, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: Sun and cloud, 23C

Work done:

  • The area adjacent to the 248 building had its soil, flowers, vegetation and trees removed.
  • The Allan blocks1 between the 244 and 248 buildings have been removed. All blocks filled with cement have been disposed of, as they can’t be re-used (ones filled with dirt can be kept and re-used).
  • Pavers forming the sidewalk leading to the staircase have been removed and stored in the central courtyard (visitor parking).

The number of workers onsite appeared to be 4-6.