Phase 1 Membrane Project, Day 61 (November 12, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, clouds and showers

Work done today:

  • Additional repair work on leaks
  • Delivery of two large propane tanks
  • Delivery of at least five large cans of liquid material (possibly primer)
  • Workers on site: At least 3

Phase 1 Membrane Project, Day 60 (November 10, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 14C, mostly cloudy

No work done today.

NOTE: The cracks in the concrete slab were repaired with Kryten Krystol compound. The material needs to cure/dry before the new membrane can be applied, so no work on the concrete slab will happen for what is likely to be at least a few more days, depending in part on the weather.

The site today, November 10th:

Phase 1 Membrane Project, Day 58 (November 7, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 11C, mix of rain and cloud

Work done:

  • Wooden forms removed from concrete curb.
  • Plastic sheets removed from crack repairs on the concrete slab.
  • Workers onsite: At least two.

Also:

  • Delivery of multiple shrink-wrapped palettes. I’m unsure of the contents, but it is possible it is membrane material, as installation of the new membrane is close now.
  • Strata Engineering had people inspecting the site.

Phase 1 Membrane Project, Day 57 (November 6, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 12C, intermittent heavy rain throughout day

Work done today:

  • Unsure what was done, but Prostar was onsite.
  • Strata Engineering was inspecting the site early in the morning.
  • Workers onsite: Unknown.

Phase 1 Membrane Project, Day 56 (November 5, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 13C, rain

Work done today:

  • Plastic covering placed over most of the crack repairs on the concrete slab
  • Other work may have been done, but unable to confirm as of this writing; will update if more details become known
  • Workers onsite: At least two