Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: Sun and cloud, 23C
Work done:
- The area adjacent to the 248 building had its soil, flowers, vegetation and trees removed.
- The Allan blocks1 between the 244 and 248 buildings have been removed. All blocks filled with cement have been disposed of, as they can’t be re-used (ones filled with dirt can be kept and re-used).
- Pavers forming the sidewalk leading to the staircase have been removed and stored in the central courtyard (visitor parking).
The number of workers onsite appeared to be 4-6.




- Allan blocks look like this: ↩︎