Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 7C, mix of sun and cloud
No work onsite today.
Prostar is apparently awaiting a Field Report from Strata Engineering to resume specific work. The patios are estimated to be 95% complete at this stage.