Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 9C, clouds and rain, at time heavy
Work done today:
Continued work on applying primer and laying down membrane on the five affected patios on Building 244.
Workers onsite: At least two.
Our patio with primer applied. Cracks have not been repaired.Patio with membrane being laid down.
The following shot is of a crack repair behind the 244 building. While the concrete curb and other crack repairs were covered with plastic for several days after the work was done, this crack was left exposed. This shot, taken on November 14, shows how the crack is both partially submerged under standing water and how the Krten Krystol mixture is starting to flake off.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 12C, Heavy rain at times, clouds
Work done today:
Work on the application of primer and membrane on patios has begun.
Workers onsite: At least three.
Strata Engineering also appeared to be onsite in the morning.
Other work may have been done, but I can’t confirm.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 10C, clouds and showers
Work done today:
Additional repair work on leaks
Delivery of two large propane tanks
Delivery of at least five large cans of liquid material (possibly primer)
Workers on site: At least 3
Site viewed from hospital path, November 12, 2025, crack repairs visible.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 14C, mostly cloudy
No work done today.
NOTE: The cracks in the concrete slab were repaired with Kryten Krystol compound. The material needs to cure/dry before the new membrane can be applied, so no work on the concrete slab will happen for what is likely to be at least a few more days, depending in part on the weather.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/