Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 12C, Heavy rain at times, clouds
Work done today:
- Work on the application of primer and membrane on patios has begun.
- Workers onsite: At least three.
- Strata Engineering also appeared to be onsite in the morning.
- Other work may have been done, but I can’t confirm.