Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 8C, rain, occasional breaks
No work done today.
It is unclear why no one was onsite today, as it is a regular workday and there is much work still to be done before the project can be completed.
The following photos were taken today, November 21, 2025.
Membrane work along the south side of the 248 building.Housekeeping pads under the staircase, still awaiting work to remove rust, etc.Current state of two of the five patios being worked on.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 9C, cloudy
Work done today:
Continued work on the membrane installation between the 244 and 248 buildings.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 11C, some clearing, cloudy
Work done today:
The first layer of membrane was applied to the concrete slab between the 244 and 248 buildings
The area behind the 244 building was further cleaned/cleared, primarily using a leaf blower
Strata Engineering was onsite, others may have been as well
Workers onsite: At least two observed
View from hospital path showing the first layer of membrane on the concrete slab bwtween the two buildings:
Two workers with blowtorches are seen working on the membrane installation.Ground level shot showing first layer of membrane.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 9C, cloudy
Work done today:
Continued work on installing membrane on the five affected patios.
Application of primary to the majority of the concrete slab between the 244 and 248 buildings.
Primer applied to most of the concrete slab, done today.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 11C, drizzle and light rain
No work onsite today.
Biweekly onsite meeting took place with:
Strata Engineering
Prostar
Copperstone Council, represented by the Vice President
Quay Pacific had no representation this week due to illness