Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now expected in January 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 15C, cloudy
Work done today:
Continued work on stripping the membrane from behind the 244 building
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now expected in January 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 17C, sun and cloud
Work done today:
Continued stripping of membrane behind the 244 building using the Terminator (yes, that is what the machine is called)
Workers onsite: 3-5
Newly stripped surface between 244 and 248 buildings (photo taken October 6, 2025)Close-up showing depth that will be dug for Phase 2 of the membrane project (photo taken October 6, 2025)
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now expected in January 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 20C, sunny
The third biweekly status meeting took place. Attending were:
Prostar
Strata Engineering
Sub contractor reps
Copperstone Council, represented by the Vice President
Quay Pacific strata property manager
Prostar indicated all membrane should be removed by the end of this week.
Work done today:
Membrane removed from the area between 244 and 248 buildings.
Excavation done at edge of visitor parking adjacent to the above area. This also acts as a preview of the work that will be required for Phase 2.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now expected in January 2026) Primary contractor: Prostar https://prostar.ca/
No work onsite today.
NOTE: Currently work is not being done on Saturdays, though under city permit, it is allowed. I am including Saturdays to avoid confusion about what is happening on those days.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now expected in January 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 17C, sun and cloud
Work done:
Completed removal of membrane from all patios that are part of Phase 1 (five total)
Tested equipment and did partial removal of membrane in open area
Workers onsite: At least three
Patio deck with mebrane removedArea between 244 and 248 on Sunday, Oct. 5, 2025, showing some membrane removal.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now expected in January 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 17C, sun and cloud
Work done (first work since September 19th):
First three patios had membrane removed
Partial removal of membrane in area between 244 and 248 buildings