Phase 1 Membrane Project Day 33 (October 8, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 15C, cloudy

Work done today:

  • Continued work on stripping the membrane from behind the 244 building
  • Workers onsite: 3-5

More photos of the area coming soon!

Phase 1 Membrane Project, Day 32 (October 7, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 17C, sun and cloud

Work done today:

  • Continued stripping of membrane behind the 244 building using the Terminator (yes, that is what the machine is called)
  • Workers onsite: 3-5

Phase 1 Membrane Project, Day 31 (October 6, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 20C, sunny

The third biweekly status meeting took place. Attending were:

  • Prostar
  • Strata Engineering
  • Sub contractor reps
  • Copperstone Council, represented by the Vice President
  • Quay Pacific strata property manager

Prostar indicated all membrane should be removed by the end of this week.

Work done today:

  • Membrane removed from the area between 244 and 248 buildings.
  • Excavation done at edge of visitor parking adjacent to the above area. This also acts as a preview of the work that will be required for Phase 2.
  • Workers onsite: Between 3-5

Phase 1 Membrane Project, Day 30 (October 4, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

No work onsite today.

NOTE: Currently work is not being done on Saturdays, though under city permit, it is allowed. I am including Saturdays to avoid confusion about what is happening on those days.

Phase 1 Membrane Project, Day 29 (October 3, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 17C, sun and cloud

Work done:

  • Completed removal of membrane from all patios that are part of Phase 1 (five total)
  • Tested equipment and did partial removal of membrane in open area
  • Workers onsite: At least three

Phase 1 Membrane Project, Day 28 (October 2, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 17C, sun and cloud

Work done (first work since September 19th):

  • First three patios had membrane removed
  • Partial removal of membrane in area between 244 and 248 buildings
  • Workers onsite: Observed 3, possibly more