Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 12C, cloudy
No work onsite today.
I don’t have anything official to back this up, but based on the work completed and some designs that are pending approval, we may not see any workers onsite for a few days.
From Update 5, which should be going out to owners soon, here’s what’s left for the project:
- Drainage work around the ventilation shaft.
- Allan block wall to be re-assembled behind the ventilation shaft.
- Membrane design for the three pipes on the south side of the 248 building.
- Filling the excavation at the end of the walkway to allow access to the stairs leading to the hospital lane. This will be a temporary design until Phase 2 begins (design is under review).
- Replacement of spray insulation that has fallen in the parkade.
- Repairing cracks in the parkade ceiling in areas noted by Strata Engineering.
On #4, workers have created a temporary bridge over the open area, allowing residents and visitors to access the stairway leading up to the hospital lane.