Phase 2 membrane project, Day 35–August 31, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 24°C, mostly sunny
Workers onsite: At least 8

Work done today:

  • Flashing restored on some patios on both Building 240 and 244
  • Second layer of membrane applied to area adjacent to Building 240
  • Sealant work finished near emergency repair area and first layer of membrane applied
  • Additional signage posted throughout area by Prostar