Phase 2 membrane project, Day 32–August 26, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 25°C, mostly sunny
Workers onsite: At least four

Work done today:

  • Clearing of concrete slab adjacent to emergency repair area
  • Stripping of membrane from concrete slab next to Building 240