Phase 2 membrane project, Day 26–August 19, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 26°C, sunny with high cloud
Workers onsite: At least two

Work done today:

  • Restoration of pavers on two patios, one completed, the other nearly completed
  • Some tidying up around the newly cored drains