Phase 2 membrane project, Day 25–August 18, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 26°C, sunny
Workers onsite: At least two

Work done today:

  • Three new drains were cored in the concrete slab near the 244 building:
    • Two near patios
    • One that will be between the two planters at the Building 244 entrance and will provide drainage that did not exist in the area before (goodbye to Lake Copperstone!)