Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 26°C, sunny
Workers onsite: At least two
Work done today:
- Three new drains were cored in the concrete slab near the 244 building:
- Two near patios
- One that will be between the two planters at the Building 244 entrance and will provide drainage that did not exist in the area before (goodbye to Lake Copperstone!)