Emergency membrane repair/Phase 1 completion (pre-Phase 2 work), Day 7

Weather: 21°C, mostly sunny
Workers onsite: At least 4

NOTE: The expansion of the work area in front of the 244 building means that the sidewalk and stairs leading to the hospital pathway is now closed until further notice.

Work done today:

  • Additional removal of pavers, aeration mat and more from the Phase 1 area in front of the 244 building
  • Additional clean-up in emergency repair area between the 240 and 244 buildings

Issues addressed (after being raised by council):

  • Temporary steps added to fire exits of 240 and 244 buildings in construction areas
  • Irrigation piping left on easement has been moved to the central courtyard
  • Removed membrane has been moved from being piled in the courtyard to the large waste bin

Note: Depending on need, two additional parking stalls may be unavailable in the Visitor Parking. Currently, 16 stalls are unavailable, so this could temporarily rise to 18. There are 21 stalls available as of this writing.