Emergency membrane repair (pre-Phase 2 work), Day 2

Weather: 24°C, sunny
Workers onsite: At least 6

Work done today:

  • The protective barrier around the Heritage Courtyard trees is complete, a second protective barrier around the tree in the northeast corner of the property is nearly done. The fencing on the main barrier currently has two open sections, but the area is otherwise inaccessible. I’ll update as I get more information on whether this area will be completely off-limits for the duration of the project.
  • The area between the 240 and 244 buildings is now stripped down to the concrete slab. Work on applying the new sealant, membrane, and other materials should begin soon.