Phase 2 membrane project, Day 56–September 25, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 14°C, showers and clouds
Workers onsite: At least six

Work done today:

  • Delivery of aggregate material (sand) to the site
  • Aggregate (sand) spread over existing drainage mat adjacent to Building 244
  • Reinstatement of wooden beans near corner of main entrance of Building 244