Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 26°C, sunny
Workers onsite: At least five
Work done today:
- Pavers put back or partially restored on four patios
- Membrane completed on four of the five Building 240 patios
- Initial clearing of the last area on the south side of the parking lot, to allow for removal of old membrane