Phase 2 membrane project, Day 3–July 22, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 33°C, sunny
Workers onsite: At least five

Work done today:

  • Two of the four Building 244 patios have had membrane applied
  • More pavers have been removed from the parking lot adjacent to Building 244