Membrane work, July 7, 2026

Weather: 24°C, mostly sunny
Workers onsite: At least four

Work done today:

  • Membrane at the Building 244 entrance was stripped in preparation for sealant and new membrane to be laid down
  • New membrane was delivered to the site
  • The membrane drop down at the north end of the Phase 1 extension was extended to be the proper full eight inches

Also of note: I once again let the mail delivery person in, so we got mail delivery for a second day. Someone else apparently let in an Amazon delivery person as I could see new packages in the lobby (mailroom) and delivered to units on the ground floor. Whoever did that, thanks!