Weather: 29°C, sunny
Workers onsite: At least six
Work done today:
- Work was focused on demolition of the area in front of the Building 244 entrance
- Pavers were removed and stacked in the central courtyard
- Sand is being stored in the emergency repair area
- The area was cleared down to the membrane
- The Terminator (see photo below) is parked in the area, ready to remove membrane
As noted before, Prostar refused to give a time estimate of how long this work will take, nor have they explained how the mail and other deliveries will get in when the workers placed red caution tape directly (and extensively) in front of the doors.
I am giving my own estimate of 3–14 days for completion. At least the weather does not look to be a factor.