Membrane work, June 24, 2026

Weather: 30°C, mostly sunny
Workers onsite: 2

Work done today:

  • Temporary path from the fire door adjacent to the 244 building entrance was completed in anticipation of the temporary closure of the building entrance starting tomorrow. That work has now been postponed until Monday, July 6, 2026. It is unclear how this path will affect work in the Phase 1 extension area over the next 11 days.
  • No other work was observed onsite, though there is a lot that can obviously be done, especially with good weather.
Temporary path from 244 fire door that will be used starting July 6, 2026.