Weather: 21°C, mostly sunny
Workers onsite: At least 4-6
Work done today:
- Irrigation piping in the Phase 1 extension area installed by Blue Drop.
- Continued work on membrane in the emergency repair area, with most upturns and the main area completed.


Weather: 21°C, mostly sunny
Workers onsite: At least 4-6
Work done today: