Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 9C, clouds and rain, at time heavy
Work done today:
- Continued work on applying primer and laying down membrane on the five affected patios on Building 244.
- Workers onsite: At least two.


The following shot is of a crack repair behind the 244 building. While the concrete curb and other crack repairs were covered with plastic for several days after the work was done, this crack was left exposed. This shot, taken on November 14, shows how the crack is both partially submerged under standing water and how the Krten Krystol mixture is starting to flake off.