Phase 1 Membrane Project, Day 62 (November 13, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 12C, Heavy rain at times, clouds

Work done today:

  • Work on the application of primer and membrane on patios has begun.
  • Workers onsite: At least three.
  • Strata Engineering also appeared to be onsite in the morning.
  • Other work may have been done, but I can’t confirm.