Phase 1 Membrane Project, Day 115 (January 22, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, mostly cloudy

No work onsite today.

Prostar management was looking at the work area today. I am unsure if all four people were from Prostar or if some may have been contractors or from Strata Engineering.

Phase 1 Membrane Project, Day 114 (January 21, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 8C, sunny

No work onsite today. This means that Prostar has had no one onsite for five of the last six workdays.

Blue Drop, however, was back setting up more PVP piping for the upcoming irrigation work.

Phase 1 Membrane Project, Day 112 (January 19, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 8C, sunny

Work onsite today:

  • New Allan blocks were delivered via WCI Contracting Ltd. and are being placed primarily as the top layer along the sidewalk leading to the staircase.
  • Workers onsite: At least two.