Phase 1 Membrane Project, Day 48 (October 27, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, clouds and showers

Work done today:

  • Additional removal of stone cladding from several pillars adjacent to the 244 building patios.
  • Wood forms moved in place near the retaining wall behind the 244 building (the area is not clean/ready for a concrete pour, so this may just be temporary).
  • Workers onsite: 3 observed, possibly more.

Phase 1 Membrane Project, Day 47 (October 25, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, rain, gusting wind at times, clouds

Work done today:

  • Shot blasting of the exposed portion beneath the Allan block wall behind the 244 building, in preparation for the concrete curb that will go in the same area.
  • Workers onsite: At least four observed.

Shot blasting material used was Enviro-Grit Abrasives Enviro-Grit. The product page is here: https://www.enviro-corp.ca/enviro-grit. It’s basically extra fine glass dust.

The photo below was taken from our patio.

NOTE: The work crew was still here at 8 p.m., which appears to be a violation of New Westminster City Bylaw 8013, part of City Bylaw 6063 (Construction Noise):

Bylaw 6063 can be viewed as a PDF here: https://www.newwestcity.ca/database/files/library/Consolidated_Bylaw_6063__1992_Construction_Noise(1).pdf

Phase 1 Membrane Project, Day 46 (October 24, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 13C, heavy rain and wind

Work done today:

  • Removal of planking along the bottom of the 244 building on the west and north sides.
  • Removal of the lower portion of stone cladding from the pillars in the areas listed above.
    • This work is being done to allow the new membrane to extend eight inches (about 20 cm).
  • Workers onsite today: At least four observed.
  • Strata Engineering also had at least four people onsite doing inspections.

Phase 1 Membrane Project, Day 45 (October 23, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 15C, mix of cloud and showers

Work done today:

  • Continued removal of membrane residue from concrete slab behind the 244 building and between the 244 and 248 buildings.
  • Power-washing of concrete slab between the 244 and 248 buildings.
  • Workers onsite: At least 3.

Phase 1 Membrane Project, Day 44 (October 22, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 12C, cloudy, some showers

Work done today:

  • Continued removal of membrane residue between the 244 and 248 buildings and along the back (west) side of the 244 building.
  • Work expanded to patios, with all but one patio in various states of having all membrane residue removed.
  • Workers observed: At least three.

Additional work to be done before new membrane can be installed (incomplete list):

  • Removal of lowest planking on the back of the 244 building, to allow expanded membrane coverage.
  • Removal of lower portion of stone cladding through same area as above (you can see an example of this removal in the first photo below).
  • Blasting of both of the above exposed surface areas, to allow clean installation of new membrane.
  • Additional membrane residue removal along edges in various areas.

Phase 1 Membrane Project, Day 43 (October 21, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 14C, mix of sun, cloud and showers

Work onsite today:

  • Continued removal of membrane material from between buildings 244 and 248, as well as along the west side of the 244 building.
  • Workers onsite: 3 observed.