Phase 1 Membrane Project, Day 109 (January 15, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, sunny

No work observed onsite today.

Blue Drop, the irrigation contractor, was again onsite laying out PVC piping and doing other preliminary work.

I noticed that additional material had been applied to the two lamp posts between the 244 and 248 buildings, likely to better protect the membrane. I believe this was done on January 14th, as photos from the 13th do not show the material.

Editorial point: In the photo below, there seems to be a significant amount of debris on the aeration mat. I assume this will be cleaned up before the soil is brought in.

Phase 1 Membrane Project, Day 108 (January 14, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 9C, cloudy, some light showers

Work done today:

  • One worker was observed with a blowtorch between the 244 and 248 buildings. I was not able to ascertain what was being done (or which company they were part of). UPDATE: It appears they placed protective material on the bases of the two lamp posts in the area.
  • More material, mainly PVC piping, was also brought in by Blue Drop, the irrigation contractor.

Phase 1 Membrane Project, Day 107 (January 13, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 9C, clouds and showers

One person was onsite today, but I could not determine what they were doing. They may have been a contractor setting up for the upcoming irrigation work.

Phase 1 Membrane Project, Day 106 (January 12, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 9C, rain

Work done today:

  • Remediation work to address deficiencies began today. This covers the root barrier, aeration mat, certain materials and more.
  • Work began on assembling the double stack of wooden beams between the 244 and 248 buildings.
  • The biweekly meeting took place onsite, with representatives of the following attending:
    • Strata Engineering
    • Prostar
    • Copperstone Council (represented by the Vice President)
    • Supervisor for Prostar workers
  • Initial setup on the replacement irrigation system began with a separate contractor, mostly staging equipment and material.