Phase 1 Membrane Project, Day 1 (August 11, 2025)

Phase 1 Membrane Replacement Project

Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

Day 1: August 11, 2025

This was mobilization day, devoted mainly to some setup and a look at the site. Work today included:

  • Cordoning off eight parking stalls in the central area of the visitor parking1
  • Inspection of site
  • Placement of a Prostar sandwich board in the central area of visitor parking with contact info
  • The installation of a porta-potty. This is locked, so if you had dreams of using an exotic new porta-potty, you will have to look elsewhere.
  1. Fun fact: I actually cordoned off many of the spots myself after getting permission from Prostar to move the pylons as needed. ↩︎