Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Day 1: August 11, 2025
This was mobilization day, devoted mainly to some setup and a look at the site. Work today included:
- Cordoning off eight parking stalls in the central area of the visitor parking1
- Inspection of site
- Placement of a Prostar sandwich board in the central area of visitor parking with contact info
- The installation of a porta-potty. This is locked, so if you had dreams of using an exotic new porta-potty, you will have to look elsewhere.


- Fun fact: I actually cordoned off many of the spots myself after getting permission from Prostar to move the pylons as needed. ↩︎