Phase 1 Membrane Project, Day 36 (October 11, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 12C, rain and cloudy conditions

A rare day of work on a Saturday!

Work done today:

  • Plumbing and piping installed for the three new drains drilled yesterday.
  • Workers onsite: Two

In theory, the project should be very close or ready for the installation of the new membrane material.

Phase 1 Membrane Project, Day 34 (October 9, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 18C, rain in morning, sun and cloud in afternoon

Work done today:

  • More removal of membrane from construction area
  • Removal of bottom stairs on the steel staircase between the 244 and 248 buildings (presumably to keep people from using them–this will be even more important once the new membrane starts getting laid down)
  • Additional clean-up of the area
  • Workers onsite: 3-5

Phase 1 Membrane Project Day 33 (October 8, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 15C, cloudy

Work done today:

  • Continued work on stripping the membrane from behind the 244 building
  • Workers onsite: 3-5

More photos of the area coming soon!

Phase 1 Membrane Project, Day 32 (October 7, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 17C, sun and cloud

Work done today:

  • Continued stripping of membrane behind the 244 building using the Terminator (yes, that is what the machine is called)
  • Workers onsite: 3-5

Phase 1 Membrane Project, Day 30 (October 4, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

No work onsite today.

NOTE: Currently work is not being done on Saturdays, though under city permit, it is allowed. I am including Saturdays to avoid confusion about what is happening on those days.

Phase 1 Membrane Project, Day 29 (October 3, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 17C, sun and cloud

Work done:

  • Completed removal of membrane from all patios that are part of Phase 1 (five total)
  • Tested equipment and did partial removal of membrane in open area
  • Workers onsite: At least three