Phase 1 Membrane Project, Day 103 (January 8, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 5C, cloudy

Work done today:

  • Continued work on cutting and placing the wooden beams around the base of the 244 building.
  • Workers onsite: At least two.

Phase 1 Membrane Project, Day 102 (January 7, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 4C, clouds and light rain

Work done today:

  • The start of cutting and placement of the wooden beams that will form a perimeter around the back (west) and north side of the 244 building. The area between the beams and the building will be filled with gravel, as it was prior to construction.
  • Workers onsite today: At least four.

Phase 1 Membrane Project, Day 101 (January 6, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, showers

Work done today:

  • More work on the metal flashing around the base of the 244 building
  • Additional work may have been done, but is not visible
  • Workers onsite: At least two

Phase 1 Membrane Project, Day 100 (January 5, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, clouds, some sun

Work done today:

  • More work on installing the metal flashing along the base of the 244 building
  • Workers onsite: At least two
  • Strata Engineering was also onsite for inspection

Phase 1 Membrane Project, Day 99 (January 3, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 9C, rain and clouds.

No work onsite today.

Phase 1 Membrane Project, Day 98 (December 31, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, mostly sunny

Another unexpected day of work during the holiday break.

Work done today:

  • More finishing work on the metal flashing and restoring the planking around patios. I believe the intention is to have the patios fully complete in the next 1-2 business days.
  • Workers onsite: At least four.