Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather today: Cloudy with some sun.
No activity onsite today.
An UNOFFICIAL site for Copperstone, New Westminster
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather today: Cloudy with some sun.
No activity onsite today.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather today: Rain in the morning, sun and cloud in the afternoon.
No activity onsite today.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather today: Heavy rain
No activity onsite today.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No observable activity today. I suspect they may be waiting on permits from the City of New Westminster.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
I observed someone working on and in the C container, but no further work on the property was done today that I could see.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Day 2 saw actual work begin: