Phase 1 Membrane Project, Day 82 (December 6, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 11C, clouds and showers in the afternoon

No work onsite today.

Phase 1 Membrane Project, Day 81 (December 5, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 9C, rain and clouds

No work onsite today.

Phase 1 Membrane Project, Day 80 (December 4, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, rain

No work onsite today.

NOTE: I believe Prostar is waiting for some updated design work from Strata Engineering before continuing, which means we may not see anyone on site, except possibly for inspections, until Monday, December 8th.

Phase 1 Membrane Project, Day 79 (December 3, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, mix of clouds and showers

Work done today:

  • Additional work on the membrane between the 244 and 248 buildings
  • Workers onsite: Observed at least 1