Phase 1 Membrane Project, Day 79 (December 3, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, mix of clouds and showers

Work done today:

  • Additional work on the membrane between the 244 and 248 buildings
  • Workers onsite: Observed at least 1