Phase 1 Membrane Project, Day 7 (August 18, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather today: Cloudy with some sun.

No activity onsite today.

Phase 1 Membrane Project, Day 6 (August 16, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather today: Rain in the morning, sun and cloud in the afternoon.

No activity onsite today.

Phase 1 Membrane Project, Day 5 (August 15, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather today: Heavy rain

No activity onsite today.

Phase 1 Membrane Project, Day 4 (August 14, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

No observable activity today. I suspect they may be waiting on permits from the City of New Westminster.

Phase 1 Membrane Project, Day 3 (August 13, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

I observed someone working on and in the C container, but no further work on the property was done today that I could see.

Phase 1 Membrane Project, Day 2 (August 12, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Day 2 saw actual work begin:

  • The C container arrived and was set up on the central courtyard
  • A subcontractor to Prostar began and completed most of the sod removal behind and along the south side of the 244 building