Phase 1 Membrane Project, Day 23 (September 25, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 21C, mix of sun and cloud

No work onsite today.

Phase 1 Membrane Project, Day 22 (September 24, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 21C, sunny

No work onsite today.

Phase 1 Membrane Project Day 21 (September 23, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23C, sunny

Prostar was onsite briefly today doing inspections related to future parts of the project.

Phase 1 Membrane Project, Day 20 (September 22, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 21C, sunny

No work done onsite today. The second bi-weekly status meeting took place involving:

  • Copperstone Council (Vice President attending)
  • Prostar
  • Strata Engineering
  • Sub contractor reps

Review of the previous two weeks took place, as well as discussion on moving ahead on specific parts of the project.

Phase 1 Membrane Project, Day 19 (September 20, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 21C, sunny

No work onsite today.

NOTE: Prostar is not working on Saturdays at this point. I am including Saturdays, as they are allowed under permit to work on them if they choose, and this addresses possible confusion on why work may not be happening.