Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 10C, sunny
No work onsite today. The weather was unusually mild and clear for mid-January, but no one was on site once again.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 10C, sunny
No work observed onsite today.
Blue Drop, the irrigation contractor, was again onsite laying out PVC piping and doing other preliminary work.
I noticed that additional material had been applied to the two lamp posts between the 244 and 248 buildings, likely to better protect the membrane. I believe this was done on January 14th, as photos from the 13th do not show the material.
Editorial point: In the photo below, there seems to be a significant amount of debris on the aeration mat. I assume this will be cleaned up before the soil is brought in.
New material applied to lamp post base on January 14th (photo taken on January 16)
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 9C, cloudy, some light showers
Work done today:
One worker was observed with a blowtorch between the 244 and 248 buildings. I was not able to ascertain what was being done (or which company they were part of). UPDATE: It appears they placed protective material on the bases of the two lamp posts in the area.
More material, mainly PVC piping, was also brought in by Blue Drop, the irrigation contractor.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 9C, clouds and showers
One person was onsite today, but I could not determine what they were doing. They may have been a contractor setting up for the upcoming irrigation work.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 9C, rain
Work done today:
Remediation work to address deficiencies began today. This covers the root barrier, aeration mat, certain materials and more.
Work began on assembling the double stack of wooden beams between the 244 and 248 buildings.
The biweekly meeting took place onsite, with representatives of the following attending:
Strata Engineering
Prostar
Copperstone Council (represented by the Vice President)
Supervisor for Prostar workers
Initial setup on the replacement irrigation system began with a separate contractor, mostly staging equipment and material.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/