Phase 1 Membrane Project, Day 10 (September 10, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

Weather: 23C, sun and cloud mix

Work done today:

  • The ground surface behind the 244 building was hosed down.
  • All trees, bushes and other vegetation from between the 244 and 248 buildings were removed.
  • Wooden beams alongside the 248 building were removed.
  • Additional Allan blocks have been temporarily stored in the central courtyard (visitor parking).