Phase 1 Membrane Project, Day 8 (September 8, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23C, sun and cloud mix

No work done onsite today. The first bi-weekly status meeting took place involving:

  • Prostar
  • Strata Engineering
  • Sub contractor reps
  • Copperstone Council (President and Vice President attending)

Based on discussions, clean-up of the work area should be complete in the next few days, after which the forms for concrete will be placed, and then concrete poured. If the weather turns wet, tarps will likely be put in place to allow the concrete to remain dry while it cures.

Prostar is suggesting that the old structure of wooden beams/gravel fill along the perimeter of the back of the 244 building be replaced with soil and grass (extending the lawn right to the edge of the building and patios). The wood and grass was an architectural feature, but has essentially no visibility, as it faces the retaining wall. Extending the lawn to the building would be cheaper and provide a more uniform look. This will be brought to council for a final decision.