Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 10°C, steady light rain most of the day
Workers onsite: At least 6
Work done today:
- Four additional drains have been cored. This should complete the new drain installs.
- Reinstating of a planter near the 240 building entrance started
- Drainage mat and root barrier placed in central courtyard. Next steps will be filter fabric and soil/sod (soil/sod will likely not happen until the end of the project).